Milton Keynes College – Sports Hall

Phase 2 of the College’s development of their new Bletchley Campus involved the provision of a new 700m2 all-purpose pitch, four court indoor sports hall and a 500m2 amenity building including a fitness studio, sports injury facility and teaching spaces. 500sqm.

Services:             Project and cost management, contract administration
Completion:         November 2004
Procurement:      Single stage design and build
Value:                    £1.8 million

Milton Keynes College – Reception and Learning Centre

This project was to be the first phase of the redevelopment of the Woughton Campus.  It involved the construction of a new reception area and front of house facilities along with IT suite, ancillary facilities and a first floor learning resource centre.  Total area was c. 1,500sqm.

Services:             Project and cost management, contract administration
Completion:         June 2008
Procurement:      Two stage design and build
Value:                    £2.6 million

Oundle School – SciTec Centre

The SciTec Centre is to be constructed in four phases totaling some 8,231sqm.  The new centre will bring together the teaching of technology, art and aesthetics with the study of science.  The facilities include 16 chemistry and biology laboratories, a new art studio, a lecture theatre, a new library, an enlarged design technology department, enhanced physics facilities, a new gallery and an energy centre.

Services:             Project and cost management, contract administration
Completion:         Phase 1 July 2007
Procurement:      Phase 1 – two stage design develop and construct
Value:                    Phase 1 – £8 million

Sharnbrook Upper School – Reception and related reconfiguration works (Phase 2B)

Phase 2B consisted of a number of separate elements of work including, library relocation of c. 270sqm, reception reconfiguration of c. 150 sqm, refurbishment of existing science facilities of c. 900sqm and reconfiguration and refurbishment of an existing building to create further dining facilities, reprographics, IT suites, student support facilities and general teaching space totaling c. 650sqm.

Services:             Project and cost management, contract administration
Completion:         Phase 2B – April 2012
Procurement:      Phase 2B – single stage design and build tender
Value:                    Phase 2B – £1.3 million

Sharnbrook Upper School – Dining Facility (Phase 2A)

Phase 2A consisted of the new build construction of a two storey 800sqm dining facility.

Services:             Project and cost management, contract administration
Completion:         Phase 2A – April 2012
Procurement:      Phase 2A – single stage design and build tender
Value:                    Phase 2A – £1.5 million

Sharnbrook Upper School – Science Centre (Phase 1)

The project was procured in two phases. Phase 1, a new build 2,500sqm science centre included 17 teaching laboratories, prep room, seminar room and lecture theatre.  The project incorporates a number of sustainable solutions that deliver c. 30% of the energy demand for the building.  The project also involved the relocation of a number of temporary classrooms and a nursery into a purpose built prefabricated facility.

Services:             Project and cost management, contract administration
Completion:         Phase 1 – November 2010
Procurement:      Phase 1 – two stage design develop and construct
Value:                    Phase 1 – £5.5 million